Rebuild York

CITY OF YORK - SECTION 108 LOAN

REBUILD YORK
STREET IMPROVEMENT PROJECT SCHEDULE
2010 PROJECTS

If you have additional questions please call the Department of Public Works at 849-2245. Thank you.

Streets Being Rebuilt

Belvidere Avenue
College Avenue to Maryland Avenue

College Avenue
Penn Street to George Street

King Street
Penn Street to Broad Street
Sherman Street to Harrison Street

Philadelphia Street
Harrison Street to Carlisle Avenue

Pine Street
Harding Court to Rathton Road

Sherman Street
Prospect Street to Market Street

Updates for the Rebuild York Project

The following posted updates are for the Rebuild York projects for 2010. The second year of the Rebuild York projects to mill and pave streets throughout the City is underway.


UPDATE POSTED NOVEMBER 15, 2010 - All street paving work is complete for 2010. Check back in April of 2011 for further updates.


UPDATE POSTED OCTOBER 28, 2010
– A schedule for street work on West Philadelphia Street between George Street and Pershing Avenue has been set:

Saturday, October 30 - Kinsley Construction will be milling. Parking restrictions will be in place and traffic will be restricted to one lane.

Monday, November 1 - Stewart and Tate will begin paving.

Work will continue through the week to completion.


UPDATE POSTED OCTOBER 25, 2010
- The following work is scheduled for the week of October 25, 2010.
Philadelphia Street – George to Beaver and Codorus Creek Bridge to Newberry Street
Base repair will begin on Wednesday, October 27
Milling will begin on Saturday, October 30
Paving will follow during the week of November 1
Parking restrictions and lane closures will be in effect.


UPDATE POSTED OCTOBER 11, 2010 - The following work is scheduled for the week of October 11, 2010:
Philadelphia Street – From Harrison to Carlisle
Milling will continue from Broad Street to George Street.
Paving will continue on Philadelphia Street with completion of paving to Broad Street.
Work will continue west of Broad toward George Street.
Parking restrictions and lane closures will be in effect.


UPDATE POSTED OCTOBER 2, 2010 - The following work is scheduled for the week of October 4, 2010:
Philadelphia Street – From Harrison to Carlisle
Milling will continue from Broad Street to George Street.
Paving will begin on Tuesday, October 5, 2010 on Philadelphia Street at Harrison Street and will continue heading west through the week.
Parking restrictions and lane closures will be in effect.


UPDATE POSTED SEPTEMBER 17, 2010 - The following work is scheduled for the week of September 20:
Philadelphia Street – From Harrison to Carlisle
Base work will continue with single lane closures.


UPDATE POSTED SEPTEMBER 3, 2010
- The following work is scheduled for the week of September 6:
College Avenue – From Penn to George
Milling and Paving will take place.

*Residents should abide by posted No Parking signs and motorists are asked to avoid this area

Philadelphia Street – From Harrison to Carlisle
Base work will continue with single lane closures.


UPDATE POSTED AUGUST 27, 2010 - following work is scheduled for the week of August 30:
College Avenue – From Penn to George
Base work will be completed with street closures.

Philadelphia Street – From Harrison to Carlisle
Base work will start with single lane closures.


UPDATE POSTED AUGUST 19, 2010 - The following work is scheduled for the week of August 23rd:
Sherman Street – From Prospect to Market
Paving will start on Monday, August 23rd

College Avenue – From Penn to George
Base work will start with street closures.


UPDATE POSTED AUGUST 6, 2010 - The following work is scheduled for the week of August 9th:
Sherman Street – From Prospect to Market
Milling and Paving will take place, sections of Sherman Street will be closed to traffic and parking will be restricted.

King Street – From Penn to Broad
Base work is continuing with lane closures. Milling and Paving may begin by the end of the week.


UPDATE POSTED AUGUST 2, 2010 - The following work is scheduled for the week of August 2nd:
Sherman Street – From Prospect to Market
Base work will be completed August 2nd and 3rd.
Milling will be completed August 5th and 6th.
Sherman Street is scheduled for Paving on August 9th to August 11th.


UPDATE POSTED JULY 12, 2010 - Concrete work to replace handicap curb ramps has started and base work will begin soon.

The streets scheduled for work are:
Sherman Street – From Prospect to Market
King Street – From Penn to Broad
College Avenue – From Penn to George
Philadelphia Street – From Harrison to Carlisle

 

**************************************************************************************


Work began on Monday, June 22, 2009 with base repair and the installation of handicap ramps on the following streets. This will be followed by milling and paving.

All motorists are advised to obey posted No Parking signs for the duration of this work.

Residents and motorists can also obtain updates to the construction schedule by calling the Rebuild York Hotline at 849-2270. The milling contractor for this project is Recon Construction and the paving contractor is Fitz and Smith, Inc. C. S. Davidson is providing engineering and inspection services for the project. Questions about the projects can be directed to the Department of Public Works at 849-2245.

Thank you!


Posted September 18, 2009

Work will resume on the Rebuild York projects on Wednesday, September 23, 2009. The following street is scheduled for milling and paving: West Princess Street – Queen Street to Broad Street

This work will conclude the Rebuild York projects for 2009.


Weekly Update

September 1, 2009 - Princess Street should be milled starting at Belvidere and ending at the Codorus Creek Bridge. Also today, the scratch course will be placed on Beaver from Princess to Market and Princess from Beaver to Pershing.

September 2, 2009 - Princess from Beaver to Pershing and Beaver from Princess to Market will be paved.

September 3 & 4, 2009 - Princess Street from Belvidere to the Codorus Creek Bridge will be paved.


Posted August 26, 2009

Date changes - Milling will begin on Monday, August 31. We will ensure the coordination with Fitz and Smith and will follow the same order of streets for work as posted August 20, 2009.


Posted August 20, 2009

Work will resume on the Rebuild York projects on Wednesday, August 26, 2009. The following streets are scheduled for milling and paving:

North Beaver Street – Market Street to Princess Street

West Princess Street – Beaver Street to Pershing Avenue
Bridge over the Codorus to Belvidere Avenue


Weekly Update Posted August 3, 2009

Work is complete on Linden Avenue, Madison Avenue, Butler Street, Merion Road and Mason Avenue. The remaining work on Beaver Street and Princess Street will be scheduled as soon as all utility work is complete. Updates will be provided as soon as a new schedule is made available.


Weekly Update Posted July 27, 2009

Paving work for the Rebuild York projects begins Monday, July 27, 2009. Work will start on Linden Avenue from Roosevelt Avenue to Penn Street followed by Madison Avenue from Roosevelt Avenue to Newberry Street. Milling work will also continue on Butler Street, Merion Road and Mason Avenue.


Weekly Update Posted July 20, 2009

The Rebuild York street projects are moving ahead. Milling is scheduled to begin on Thursday, July 23 on the following streets in order; Merion Road, Linden Avenue, Madison Avenue, Butler Street. Paving will follow the milling operation and will continue until completed. Residents are asked to observe and obey No Parking restrictions for this work. In addition base work will continue on Mason Avenue and Princess Street through this week. Milling and Paving is tentatively scheduled for the week of August 10 for Mason Avenue, Beaver Street, and Princess Street between Pershing and Beaver.


Weekly Update Posted July 13, 2009

The handicap ramp work is moving rapidly and all ramps have been replaced on Linden, Madison, Butler, Mason, Merion, and Beaver Street. Work continues on Princess Street. The paving contractor, Fitz & Smith is slightly behind schedule and will complete base work this week on Madison, Linden and Butler. Milling and Paving on these streets will follow completion of the base work.


Weekly Update Posted July 6, 2009

Contractors have completed work on handicap ramps along Butler Street, and continue work on Mason Avenue. Base repair work continues on Madison Avenue and Linden Avenue. Final Paving for Madison, Linden and Butler is still scheduled for July 15 to July 24.


Weekly Update Posted June 26, 2009

Contractors have completed work on handicap ramps along Madison Avenue and Linden Avenue. Work will continue on handicap ramps on Butler Street this week. Base repair work will also begin on Madison Avenue and Linden Avenue. Final Paving for Madison, Linden and Butler is still scheduled for July 15 to July 24.